School Sisters of Notre Dame Campus Redevelopment

The Mandel Development Group formally submitted a request for the rezoning, redevelopment and amendment to the Village Comprehensive Plan for the School Sisters of Notre Dame Campus. The Village Board of Trustees reviewed the application materials on January 25th, 2021 and took action to forward the requests onto the various standing committees for formal review and action. Please reference the Development and Rezoning Forecasting Timeline below for an overview of the Village review process.   

May 27th, 2021 - Plan Commission Review - 6:00 P.M. Court Room

  • Tentative - Public Comment Session at the May 27th, 2021 Plan Commission Meeting

May 17th, 2021 - Building Board Review (Special Meeting) - 6:00 P.M. Court Room

May 13th, 2021 - Plan Commission Review - 6:00 P.M. Court Room

This meeting will be live streamed on the Village website and broadcast on the Village cable channel 25.

May 3rd, 2021 - Plan Commission Review - 6:00 P.M. Court Room

April 20th, 2021 - Building Board Review - 5:30 P.M. Court Room

April 15th, 2021 - Plan Commission Review - 6:00 P.M. Court Room

April 12th, 2021 - Public Works and Utilities Committee Review - 6:00 P.M. Park View Room

This meeting will be live streamed on the Village website and broadcast on the Village cable channel 25.

April 8th, 2021 - Building Board Review - 5:30 P.M. Court Room

  • Discussion of March 16th, 2021 presentation materials

March 29th, 2021 - Plan Commission Review - 6:00 P.M. Court Room

This meeting will be live streamed on the Village website and broadcast on the Village cable channel 25. 

March 16th, 2021 - Building Board Review - 5:30 P.M. Court Room

March 2nd, 2021 - Building Board Review - 5:30 P.M. Court Room

March 1st, 2021 - Plan Commission Review - 6:00 P.M. Court Room 

February 17th, 2021 - Building Board Working Session - 5:30 P.M. Park View Room

February 10th, 2021 - Plan Commission and Building Board Joint Working Session - 6:00 P.M. Park View Room

January 25th, 2021 - Board of Trustees Formal Requests for Applicable Comprehensive Plan Amendment, Rezoning and Redevelopment 

October 6th, 2020 - Building Board Conceptual Architectural Plan Review Submittal

September 14th, 2020 - Plan Commission Conceptual Redevelopment Review Submittal

Overview of the Development Review Process

 To learn more about the rezoning petition and redevelopment review process and timeline, please see the Development and Rezoning Forecasting Timeline (2020) document.

Please be sure to sign up for notifications related to the School Sisters of Notre Dame Campus Redevelopment by accessing the "Stay Informed" portal here.