Elm Grove Road - Watermain

* * * Project Updates * * *

Purpose

The Village of Elm Grove will be installing a watermain on Wall Street and Elm Grove Road during the months of June and July. This project is being done to provide water service to the new senior living project on Wall Street and is expected to be completed by the end of August. The project consists of watermain construction down Elm Grove Road from Bishops Lane in Brookfield to Wall Street and all of Wall Street.

Timeline

Currently the contractor expects to start work beginning May 28th. The contractor provided the schedule and details to the Public Works/Utilities Committee.

Traffic on Wall Street will be maintained open at all times with some possible delays. Elm Grove Road will be closed to through traffic once the contractor reaches the intersection of Wall Street and Elm Grove Road. The road will remain closed to through traffic until they are off road with construction and the road is considered safe for travel. It is expected that this closure should last approximately two weeks without any unforeseen issues.

Access will be maintained to all homeowners and businesses in the closed area of the road, but there will be no through traffic allowed during that time. Detour signs will be posted with the official detour route being Sunnyslope Road and Watertown Plank Road.

Adjusted Schedule - June 5, 2013

June 6-7  Traffic control / Erosion Control

June 10  Saw cutting

June 11-13  Dig pits for directional bore

June 14-21  Drill under Bluemound Road

June 24-28  Drill under Elm Grove Road

July 1-8  Drill under Underwood Creek

June 13-July 8  Install mainline starting at east end of Wall Street or south side of Bluemound Road Pressure test and gather samples

July 9-12  Tie in existing main

July 15  All restoration

July 15-25

Notifications

If you would like regular updates for the project you can sign up for alerts through the Notify Me page on our website. We will attempt to get information up about any changing aspects of the project during construction.

The Village appreciates your patience and apologizes for the inconvenience, but we are hopeful that this project will go quickly and be a minimal disruption this summer.

Contacts for the Project

Design / Supervising Engineer
Andy Petersen
Email Andy Petersen
Phone number: 1-262-572-5433

Construction Inspector
John Kastner
Email John Kastner
Phone number: 1-920-450-1343

American Sewer Service
Dan Robinson, Foreman
Phone number: 1-414-322-6017

Resources

Resident Letter & Public Works Utility Committee Memo (PDF)
Final Drawings with Addendum (PDF)